These chapters are auto-generated

Miami Beach, Florida

0:00

Flooding beach and City

0:09

RSA Movable Barrier Flood wall System

0:19

Concrete flood panels made to rise producing monolithic flood wall line

0:23

Bulldozers and backhoes clear mounting area

0:37

Driving sheet piles

0:43

Driving pipe piles

0:52

Adding rebar to top of pipe piles

1:11

Cast concrete to top of pipe piles

1:26

Add pile cap forms

1:46

Add pile cap rebar

1:56

Cast pile cap

2:03

Add lower foundation forms

2:07

Cast lower foundation walls

2:12

Add mid foundation rebar

2:15

Add mid foundation forms

2:20

Cast mid foundation walls

2:30

Add upper foundation rebar

2:34

Add upper foundation forms

2:37

Cast upper foundation walls

2:47

Remove forms

2:55

Continuous foundation

3:04

Hurricane storm with RSA MBFS raised

3:08

Flood control for Miami Beach

3:22

Dry side perspective

3:26

Soil removed for clarity

3:33

Vaults to enter inside MBFS

3:51

lifting cables termination points

5:01

Hurricane Storm over

7:23

RSA Flood wall panels lowered

7:28

Miami Beach Florida with RSA Hurricane Flood protection

7:39